INSP-Final Inspection | 1/2/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for core and shell only complete. TI work is in progress under different permits.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 12/27/2018 | 12/28/2018 | 12/28/2018 | P | FAIL |
Jim Page
|
|
|
Did not have basement city approved drawings, horn strobe in basement was inoperable but couldn't tell if it was part of the TI system or part of core and shell.
derik Phone #: ###-####
|
INSP-Final Inspection | 12/21/2018 | 12/27/2018 | 12/27/2018 | P | FAIL |
Jim Page
|
|
|
Elevator did not work with recall. Could not test flor flow switches, systems were drained.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan assigned to (Lee) | 3/7/2018 | | 3/7/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/7/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 3/7/2018 | | 3/7/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/7/2018 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 3/7/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 3/7/2018 | | DONE |
|
|
|
|
Application received | | | 3/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 1 2018 8:16AM
|