Fees Due Hold | 4/24/2018 | | 8/1/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
INSP-Final Inspection | 4/23/2018 | 4/24/2018 | 4/24/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for dry system complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | DONE |
Jim Page
|
|
|
24 hour air test witnessed, no pressure loss observed at dry pipe valve provided gauge.
|
INSP-Sprinkler Rough-in | 4/20/2018 | 4/23/2018 | 4/23/2018 | A | PART |
Jim Page
|
|
|
24 hr air test started at 1230PM @ 40PSI
|
Fees Due Hold | 4/21/2018 | | 4/23/2018 | | DONE |
Brittany Hill
|
|
|
|
INSP-Final Inspection | 4/17/2018 | 4/20/2018 | 4/20/2018 | A | FAIL |
Jim Page
|
|
|
Final inspection will not be performed until completion of 24 hour air test.
|
Fees Due Hold | 4/18/2018 | | 4/20/2018 | | DONE |
Tisha Gallop
|
|
|
|
Fees Due Hold | 4/13/2018 | | 4/17/2018 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/24/2018 | | 4/12/2018 | | DONE |
Christina Prado
|
|
|
|
INSP-Sprinkler Rough-in | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | PASS |
Jim Page
|
|
|
Rough in inspection for area of work complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/9/2018 | 4/10/2018 | 4/10/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
|
Sprinkler Plan Check | 3/23/2018 | | 3/23/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/23/2018 | | DONE |
|
|
|
All Requirements Met
|
Issue and Print Permit | | | 3/23/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/20/2018 | | 3/20/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/20/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 3/20/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/20/2018 | | 3/20/2018 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/20/2018 | | DONE |
|
|
|
Email from the owner
From: Gavin Moody (gmoody)
Sent: Friday, March 16, 2018 8:23 AM
To: Chris Gregory; Clarence McLain; Chris Ford
Cc: Paul Marcolina (pdmarcolina)
Subject: B51 Covered dock areas
Chris,
It has been confirmed that there will be NO Chemical storage allowed on the covered dock areas. Furthermore, the areas are not classified as they are technically outside and would not be assigned an Occupancy rating. Let me know if that clears up Tim’s concerns.
Thanks,
Gavin Moody
Facilities Mechanical Engineer
Micron Technology, Inc.
Ph ###-####
All materials and attachments contained within this email are confidential and proprietary.
|
Intake Approval | | | 3/7/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/7/2018 | | 3/7/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/7/2018 | | 3/7/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/7/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/7/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 3/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 5 2018 10:16AM
|