[Micron Building 51 - System 20-13 - C24074]
The fire sprinkler scope of work consists of part of the level 20. The system is a small side feed dry system for the dock. The owner has confirmed there will be no chemical storage.

• The underground is under permit FIR16-00701
• See addendum for graphic scope of work
[BLD16-03440]
For the construction of a new one story building with a basement for a fabrication and R&D facility to include related site work. The building includes a 157,037 sq. ft. basement, a 170,997 sq. ft. first story and a 33,638 sq. ft. equipment platform. This building is fully fire sprinklered and alarmed for H occupancy. CDM

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are a number of AMM on this project. However, none affects this fire protection system.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fees Due Hold4/24/2018 8/1/2018 DONE
DetailsTiffany Carson-Herker
INSP-Final Inspection4/23/20184/24/20184/24/2018APASS
DetailsJim Page
Final fire sprinkler inspection for dry system complete.
INSP-Sprinkler Rough-in/Hydro4/24/20184/24/20184/24/2018PDONE
DetailsJim Page
24 hour air test witnessed, no pressure loss observed at dry pipe valve provided gauge.
INSP-Sprinkler Rough-in4/20/20184/23/20184/23/2018APART
DetailsJim Page
24 hr air test started at 1230PM @ 40PSI
Fees Due Hold4/21/2018 4/23/2018 DONE
DetailsBrittany Hill
INSP-Final Inspection4/17/20184/20/20184/20/2018AFAIL
DetailsJim Page
Final inspection will not be performed until completion of 24 hour air test.
Fees Due Hold4/18/2018 4/20/2018 DONE
DetailsTisha Gallop
Fees Due Hold4/13/2018 4/17/2018 DONE
DetailsBrittany Hill
Fees Due Hold3/23/2018 4/12/2018 DONE
DetailsChristina Prado
INSP-Sprinkler Rough-in4/10/20184/10/20184/10/2018PPASS
DetailsJim Page
Rough in inspection for area of work complete.
INSP-Sprinkler Rough-in/Hydro4/9/20184/10/20184/10/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Sprinkler Plan Check3/22/2018 3/22/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/22/2018 DONE
DetailsTim Frost
Permit Ready to Issue  3/22/2018 DONE
Met
Issue and Print Permit  3/22/2018 DONE
Miscellaneous action  3/20/2018 PEND
Email from the owner

From: Gavin Moody (gmoody)
Sent: Friday, March 16, 2018 8:23 AM
To: Chris Gregory; Clarence McLain; Chris Ford
Cc: Paul Marcolina (pdmarcolina)
Subject: B51 Covered dock areas

Chris,
It has been confirmed that there will be NO Chemical storage allowed on the covered dock areas. Furthermore, the areas are not classified as they are technically outside and would not be assigned an Occupancy rating. Let me know if that clears up Tim’s concerns.

Thanks,

Gavin Moody
Facilities Mechanical Engineer
Micron Technology, Inc.
Ph ###-####

All materials and attachments contained within this email are confidential and proprietary.
Intake Approval  3/20/2018 PASS
Plan resubmittals received  3/20/2018 DONE
Plan assigned to (Tim)3/20/2018 3/20/2018 DONE
DetailsTim Frost
Sprinkler Plan Check3/8/2018 3/8/2018 FAIL
DetailsTim Frost
1st review completed  3/8/2018 FAIL
DetailsTim Frost
Miscellaneous action  3/8/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  3/7/2018 PASS
Plan assigned to (Tim)3/7/2018 3/7/2018 DONE
DetailsTim Frost
Application received  3/5/2018 DONE
Application submitted via PDS Online on Mar 5 2018 10:49AM