INSP-Final Inspection | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Roy Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Coordinate with Roy Phone #: ###-#### Inspection requested via web by Christophe Wilson
|
INSP-Sprinkler Rough-in | 4/25/2018 | 4/26/2018 | 4/26/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
|
Sprinkler Plan Check | 3/14/2018 | | 3/14/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/14/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 3/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/12/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/12/2018 | | 3/12/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/12/2018 | | 3/12/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/12/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/12/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 3/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 9 2018 11:17AM
|