Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR18-00208
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 999 W MAIN ST
Project NameVACASA TI
Customer Number 
ePlanReviewYes
Description
[Vacasa TI]
The fire sprinkler scope of work consists of removing existing CPVC piping on two floors and replacing with new steel piping. Each floor is designed as a loop with side feel branch lines.

[BLD18-00581]
Permit is to remodel levels 2&3. Work to include: removal of existing improvements, and build back of new partitions, ceilings and lighting. Remove and replace existing mechanical diffusers, fire alarms devices, exit signs to allow for new ceilings.

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/10/20188/10/20188/10/2018PPASS
DetailsJim Page
Fianl fire sprinkler inspection complete.
INSP-Final Inspection5/31/20186/1/20186/1/2018APART
DetailsJim Page
Final fire sprinkler inspection for level 3 fire sprinklers complete. Level 2 inspection to be completed at a later date.

3rd floor- Randy Phone #: ###-####
INSP-Sprinkler Rough-in6/1/20186/1/20186/1/2018APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 2 complete, level 2 approved for cover.
INSP-Sprinkler Rough-in/Hydro5/31/20186/1/20186/1/2018ADONE
DetailsJim Page
Hydrostatic test for level 2 witnessed, no pressure loss observed at riser provided gauge.

2nd floor- Randy Phone #: ###-####
INSP-Sprinkler Rough-in5/23/20185/24/20185/24/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above level 2 hardlids complete, hardlids on level 2 approved for cover.

Please call ahead for access - Randy Phone #: ###-####
INSP-Sprinkler Rough-in5/3/20185/4/20185/4/2018APART
DetailsJim Page
Rough to cover inspection for level 3 complete, level 3 approved for cover.
INSP-Sprinkler Rough-in/Hydro5/3/20185/3/20185/3/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 3 witnessed, no pressure loss observed at riser provided gauge.

Early as possible // Randy Phone #: ###-####
INSP-Sprinkler Rough-in4/26/20184/27/20184/27/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids complete, notated city approved drawings areas approved for cover.
Sprinkler Plan Check3/15/2018 3/15/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/15/2018 DONE
DetailsTim Frost
Permit Ready to Issue  3/15/2018 DONE
Issue and Print Permit  3/15/2018 DONE
(F) Reprint permit  3/15/2018 DONE
Intake Approval  3/14/2018 PASS
Plan assigned to (Tim)3/14/2018 3/14/2018 DONE
DetailsTim Frost
Sprinkler Plan Check3/14/2018 3/14/2018 FAIL
DetailsTim Frost
1st review completed  3/14/2018 FAIL
DetailsTim Frost
Miscellaneous action  3/14/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  3/13/2018 DONE
Application submitted via PDS Online on Mar 13 2018 4:29PM