Permit Information
Permit NumberFIR18-00219
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 5246 W OVERLAND RD
Project NameSTEP AHEAD TI /LIBRARY
Customer Number 
ePlanReviewYes
Description
[Boise City Library - Step Ahead At Hillcrest]
The fire sprinkler scope of work consists of protecting a TI space to increase the overall size of the library. A new 4” main is being added along with several new 1 ¼” and 1” branch lines. The new main protects approximately half of the space.

[BLD17-03972]
Permit for tenant improvements to expand the existing library and create an area for the Step program with work to include the removal and construction of interior nonbearing partition walls HVAC, electrical and the installation of related interior finishes per the approved plans. This building is fully fire sprinklered for unlimited area. Any alterations to the sprinkler system will require a separate and shall comply with NFPA 13 as regulated by the fire department. CDM

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• See addendum
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/14/20188/16/20188/16/2018APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection8/8/20188/8/20188/8/2018PFAIL
DetailsTroy Cobbley
Pendants are still being installed, missing canopies and ceiling tile.

Jordan Fuger is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/28/20186/28/20186/28/2018PPASS
DetailsTroy Cobbley
Rough-in passed. Piping can be covered in the tenant space. Drops are not complete in the Entry way. Tim Frost stated he is ok with the two pendants in the ajoining space not being mounted in a ceiling since there is upright protection.
INSP-Sprinkler Rough-in6/26/20186/27/20186/27/2018ACANC
DetailsTroy Cobbley
The revised drawings are not available yet so Jeff is going to re-schedule for tomorrow morning.

Phone #: ###-#### Inspection requested via web by Stan Beus
Sprinkler Plan Check6/26/2018 6/26/2018 DONE
DetailsTim Frost
Plan Modification Accepted  6/26/2018 DONE
Plan assigned to (Tim)6/26/2018 6/26/2018 DONE
DetailsTim Frost
Intake Approval  6/26/2018 PASS
PLANS/APPL TAKEN TO FRONT DESK  6/26/2018 DONE
Permit Ready to Issue  6/26/2018 DONE
Plan Mod Approved
DO NOT REISSUE
CHANGE STATUS TO (ISS)  6/26/2018 DONE
Plan Modification Accepted  6/21/2018 DONE
INSP-Sprinkler Rough-in6/18/20186/19/20186/19/2018AFAIL
DetailsTroy Cobbley
Water curtain area piping not installed yet. No small documents on site. Plan modifications are needed to show the additional 90's in the sprinkler mains, branchlines and sprinkler drops of both remote areas. Earthquake bracing model/type installed is not the type used. Earthquake bracing missing or installed in wrong location. Bracing may be exceeding 7' in length. Retaining straps and branchline restraints are missing. The two dry sidewalls show on the plans have been deleted and two pendants installed in their place but are attached to a dry system with no return bends. This dry system piping is not shown on the approved plans. No piping can be covered. I did allow borders to be installed.

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/15/20186/18/20186/18/2018ACANC
DetailsTroy Cobbley
Sprinkler contractor was not on site. No inspection performed.

Phone #: ###-#### Inspection requested via web by Stan Beus
Plan Modification Accepted  5/15/2018 DONE
Plan assigned to (Tim)5/15/2018 5/15/2018 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  5/15/2018 DONE
Sprinkler Plan Check5/15/2018 5/15/2018 PASS
DetailsTim Frost
Permit Ready to Issue  5/15/2018 DONE
met
Issue and Print Permit  5/15/2018 DONE
(F) Reprint permit  5/15/2018 DONE
Issue and Print Permit  3/22/2018 DONE
Sprinkler Plan Check3/20/2018 3/20/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/20/2018 DONE
DetailsTim Frost
Permit Ready to Issue  3/20/2018 DONE
met
Sprinkler Plan Check3/19/2018 3/19/2018 FAIL
DetailsTim Frost
Miscellaneous action  3/19/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  3/16/2018 PASS
Plan assigned to (Tim)3/16/2018 3/16/2018 DONE
DetailsTim Frost
Sprinkler Plan Check3/16/2018 3/16/2018 FAIL
DetailsTim Frost
1st review completed  3/16/2018 FAIL
DetailsTim Frost
Miscellaneous action  3/16/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  3/15/2018 DONE
Application submitted via PDS Online on Mar 15 2018 12:34PM