INSP-Final Inspection | 6/1/2018 | 6/5/2018 | 6/5/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. This scope of work was for phase 1
Please set for as early as possible. Tony Burtlow is the Tech on Site. Phone #: ###-#### Inspection requested via web by David Oliver
|
INSP-Final Inspection | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | FAIL |
Troy Cobbley
|
|
|
As-builts are needed showing the candella changes and address changes. One strobe is missing as noted on the plans. For a final the notification circuit needs tested, as-builts, correct batteries, document box, breaker lock, manual pull stations in the adjacent restraunt relocated and tested.
|
Miscellaneous action | | | 6/1/2018 | | DONE |
|
|
|
As built drawing received and approved.
|
INSP-Final Inspection | 5/31/2018 | 6/1/2018 | 5/31/2018 | P | CANC |
Troy Cobbley
|
|
|
Tony Burtlow is our Technician on site. Phone #: ###-#### >> Inspection requested via web by David Oliver Inspection cancelled from web by: David Oliver
|
Plan resubmittals received | | | 4/12/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 4/12/2018 | | 4/12/2018 | | PASS |
Lee G Meredith
|
|
|
Approved as noted.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/12/2018 | | DONE |
|
|
|
Plans approved as noted with review comments.
|
Permit Ready to Issue | | | 4/12/2018 | | DONE |
|
|
|
All Requirements Met
|
Issue and Print Permit | | | 4/12/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 4/10/2018 | | 4/10/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 4/10/2018 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 4/10/2018 | | DONE |
|
|
|
1st review comments emailed to applicant.
|
Application received | | | 3/15/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 15 2018 3:50PM
|