INSP-Final Inspection | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Call Anthony when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 4/9/2018 | 4/10/2018 | 4/10/2018 | A | FAIL |
Troy Cobbley
|
|
|
tile and esch. missing
Please call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/29/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. All pipingdu can be covered
|
INSP-Sprinkler Rough-in | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered except in the room next to the Service Counter. That work for the two pendants was not complete yet.
|
Issue and Print Permit | | | 3/21/2018 | | DONE |
|
|
|
|
Application received | | | 3/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 19 2018 8:43AM
|
Intake Approval | | | 3/19/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/19/2018 | | 3/19/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/19/2018 | | 3/19/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/19/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/19/2018 | | DONE |
|
|
|
|