INSP-Final Inspection | 4/9/2018 | 4/9/2018 | 4/9/2018 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for scope of work complete.
|
Issue and Print Permit | | | 3/27/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/26/2018 | | DONE |
|
|
|
|
1st review completed | | | 3/26/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 3/26/2018 | | 3/26/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/26/2018 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 3/26/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/22/2018 | | DONE |
|
|
|
Broadie Stenquist sent product data on the listed assembly they are providing. It appears the included solenoid is not approved to be used with the Siemens panel. Informed Rick of this and told him the application is being rejected.
|
1st review completed | | | 3/22/2018 | | FAIL |
|
|
|
Siemens panel is not compatible with the solenoid provided in the listed pre-action assembly from Treasure Valley Fire Protection. Rick notified by email.
|
Telephone call | | | 3/21/2018 | | DONE |
|
|
|
Rick called to inform me that he didn not have the model number for the solenoid. He did email product data that indicated which solenoids were listed with the panel model he submitted. I emailed Brodie at TVFP requesting the solenoid model number since they are supplying it.
|
Application received | | | 3/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2018 12:55PM
|
Miscellaneous action | | | 3/20/2018 | | DONE |
|
|
|
Solenoid product data not provided. Requested this information from Rick.
|
Plan assigned to (Lee) | 3/20/2018 | | 3/20/2018 | | DONE |
Lee G Meredith
|
|
|
|