INSP-Final Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | DONE |
Troy Cobbley
|
|
|
Reinspect for AES Phone #: ###-#### Inspection requested via web by Jeff Gooch
|
INSP-Alarm Testing | 1/15/2020 | 1/21/2020 | 1/21/2020 | A | FAIL |
Troy Cobbley
|
|
|
Will be ok to final when test papers are received.
Call Jake Adams. District and Alarm Co personnel will be on site. Phone #: ###-#### Inspection requested via web by Jeff Gooch
|
INSP-Sprinkler Rough-in | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | FAIL |
Troy Cobbley
|
|
|
The AES functioned but the main fire alarm system has provlems such as display and notification output. This permit can be finaled when the fire alarm system has been repaired. Depending of the required work this AES may need to be retested.
Jacob Phone #: ###-####
|
Plan assigned to (Lee) | 5/9/2019 | | 5/9/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/9/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 5/9/2019 | | 5/9/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/9/2019 | | DONE |
|
|
|
As built - No fee
|
Permit Ready to Issue | | | 5/9/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/9/2019 | | DONE |
|
|
|
AS BUILT PER LEE
|
Plan resubmittals received | | | 5/7/2019 | | DONE |
|
|
|
Per Lori at Alarmco start workflow for as built
|
Case Summary | | | 6/20/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/26/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 3/21/2018 | | 3/21/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/21/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 3/21/2018 | | 3/21/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/21/2018 | | DONE |
|
|
|
Quick permit approved as noted.
|
Permit Ready to Issue | | | 3/21/2018 | | DONE |
|
|
|
|
Application received | | | 3/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2018 7:58PM
|