INSP-Final Inspection | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type scheduled.
|
INSP-Final Inspection | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | CANC |
Jim Page
|
|
|
Paint booth is not ready for final inspection, this request is cancelled.
Phone #: ###-#### Inspection requested via web by Eric Stanley
|
INSP-Final Inspection | 4/30/2018 | 5/2/2018 | 5/3/2018 | P | PART |
Troy Cobbley
|
|
|
Functionality fo the sppression system tested. As-builts received. Will be able to final when a life safety inspection is passed for the paint booth itself.
Nate Phone #: ###-####
|
Plan assigned to (Tim) | 3/22/2018 | | 4/4/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/4/2018 | | 4/4/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/4/2018 | | DONE |
|
|
|
|
Telephone call | | | 4/4/2018 | | DONE |
|
|
|
called to let know permit is ready and how much is owed
|
Miscellaneous action | | | 4/4/2018 | | DONE |
|
|
|
caloled Tim F to see what fees to charge-he said to use the cooking hood fee so they could get charged the 150.00 fee
|
Issue and Print Permit | | | 4/4/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/27/2018 | | DONE |
|
|
|
Plans and drawings taken to Tim Frost
|
Sprinkler Plan Check | 3/26/2018 | | 3/26/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/26/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/26/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Telephone call | | | 3/26/2018 | | DONE |
|
|
|
called Iridium Protection and told Nate plan failed review and paperwork up at front to pick up
|
Application received | | | 3/22/2018 | | |
|
|
|
|