INSP-Final Inspection | 5/9/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 5/4/2018 | 5/8/2018 | 5/8/2018 | A | CANC |
Jim Page
|
|
|
Final inspection cancelled per conversation with point of contact, inspection request will be rescheduled for a later date.
air test Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 5/8/2018 | 5/8/2018 | 5/8/2018 | A | DONE |
Jim Page
|
|
|
24 hour air test witnessed, no pressure loss observed at contractor provided gauge.
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2018 | 5/7/2018 | 5/7/2018 | A | PART |
Jim Page
|
|
|
24 hour air test started at 1030AM with 50 psi.
air test Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2018 | 5/4/2018 | 5/4/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at contractor provided gauge.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 5/2/2018 | 5/4/2018 | 5/4/2018 | A | CANC |
Jim Page
|
|
|
Final fire sprinkler inspection for dry system cannot be completed until 24 hour air test is perfromed and passed, this request is cancelled.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
Sprinkler Plan Check | 4/9/2018 | | 4/9/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/9/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 4/9/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/28/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/28/2018 | | 3/28/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/28/2018 | | 3/28/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/28/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/28/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 3/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 27 2018 4:05PM
|