INSP-Final Inspection | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Conference | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | DONE |
Troy Cobbley
|
|
|
Can give me a call about an hour ahead please. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 4/26/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
Troy Cobbley
|
|
|
All work is complete except for the dry sidewall heads under the exterior canopy which has not been finished yet.
Brian Phone #: ###-####
|
Override - Parcel Holds | 4/26/2018 | 1/1/1900 | 4/26/2018 | | |
|
|
|
FIR final
|
Intake Approval | | | 4/19/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/19/2018 | | 4/19/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/19/2018 | | 4/19/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/19/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/19/2018 | | DONE |
|
|
|
Met
|
Issue and Print Permit | | | 4/19/2018 | | DONE |
|
|
|
|
Application received | | | 4/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2018 12:35PM
|