[Vector Church] - Quick Permit
Tenant Improvement to a 17,707 Sq. Ft. Bldg. Existing piping to remain scope of work to include Elevate main, add add'l heads to accommodate new wallls

[BLD17-03023]
(VECTOR CHURCH – TENANT IMPROVEMENT – OLD KMART – EAST END) (CZC17-00130) (2-28-18 DEFERRED SUBMITTAL TO CONSTRUCT THE 914 SQUARE FOOT WORSHIP PLATFORM, THE 200 SQUARE FOOT ADJACENT PLATFORM, AND THE 111 SQUARE FOOT SOUND BOOTH PLATFORM. ALL PLATFORMS WILL BE 30 INCHES TALL AND WILL BE PERMANENT. WORK INCLUDES WOOD STUD PONY WALLS, WOOD FLOOR JOISTS, WOOD FLOOR DECKING, A WOOD FRAMED RAMP, WOOD FRAMED STAIRWAYS, AND ADEQUATE BRACING IN BOTH DIRECTIONS TO RESIST LATERAL LOADS. THE CONCEALED COMBUSTIBLE SPACES BELOW THE PLATFORMS ARE REQUIRED TO BE IN COMPLIANCE WITH NFPA 13 (I.E. THE FIRE SPRINKLER STANDARD). The fire sprinkler system is used for unlimited area of the building AND to allow 3-hr fire barrier walls in lieu of fire walls. The fire sprinkler system is NOT allowed to be used for building area increase for A Occupancies. To do tenant improvement work inside a 12,633 square foot tenant space for a new church. This tenant space was created under shell permit BLD17-01449. Work is to include a coffee bar, coffee preparation equipment, a gypsum board soffit, interior nonbearing walls, interior doors, a shear wall at the edge of an existing mezzanine where a portion of the mezzanine was removed, structural upgrades to the remaining mezzanine diaphragm in the adjacent space, suspended acoustical ceiling, millwork, and finishes. A new 30.67 foot wide opening and a new 6.33 foot wide opening will be created in an existing interior masonry bearing wall. Work is to include expanded concrete footings, steel columns, steel beam, and steel headers and jambs. Special Inspection is required for anchors post-installed in hardened concrete and for welding. Some building shell work was done under permit BLD17-01449. Work included structural modifications to the roof (beams and joists) to support new roof top HVAC equipment, new openings in the North exterior masonry bearing wall with a new 2-hr steel beam or lintel supported by new 2-hr steel columns or jambs and expanded concrete footings, new storefront glazing and entrance doors, 3-hr fire barrier walls per the 2012 IEBC in lieu of fire walls to create separate buildings, 3-hr exit doors in the fire barrier wall, interior nonbearing walls, and 2 toilet rooms accessible to the disabled. Modular stage, modular ramp, modular sound room, and modular stairways, are deferred submittal items and are required to be reviewed and approved before installation. This permit is intended to establish a Certificate of Occupancy for this tenant. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/5/20186/6/20186/6/2018APASS
DetailsTroy Cobbley
Permit finaled

Contact Leroy Anderson ###-#### 30 min prior to Fire Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in5/7/20185/8/20185/8/2018APASS
DetailsTroy Cobbley
Rough-in passed.
Sprinkler Plan Check5/4/2018 5/4/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  5/4/2018 DONE
DetailsTim Frost
Permit Ready to Issue  5/4/2018 DONE
Issue and Print Permit  5/4/2018 DONE
Sprinkler Plan Check4/23/2018 4/23/2018 FAIL
DetailsTim Frost
Intake Approval  4/23/2018 PASS
Plan resubmittals received  4/23/2018 DONE
Sprinkler Plan Check4/19/2018 4/19/2018 FAIL
DetailsTim Frost
Intake Approval  4/19/2018 PASS
Plan assigned to (Tim)4/19/2018 4/19/2018 DONE
DetailsTim Frost
Application received  4/18/2018 DONE
Application submitted via PDS Online on Apr 18 2018 10:02AM