INSP-Final Inspection | 7/19/2018 | 7/23/2018 | 7/23/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | FAIL |
Jim Page
|
|
|
Fire sprinkler ispection is complete, only issue is the fire bell circuit will not stay enre==ergized, keeps tripping circuit breaker. When bell is repaired then permit can be finaled.
Call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 6/26/2018 | 6/28/2018 | 6/28/2018 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of cotact, inspection request will be rescheduled for a later date.
Please call Anthony to coordinate, thanks Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 5/13/2018 | 5/14/2018 | 5/14/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
Tenting inspection, call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
|
INSP-Sprinkler Rough-in/Hydro | 5/8/2018 | 5/9/2018 | 5/9/2018 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, tenting still neds to be installed and inspected before cover is approved.
Call Anthony to coordinate. Thank you. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 5/2/2018 | | DONE |
|
|
|
|
Application received | | | 4/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2018 8:26AM
|
Intake Approval | | | 4/30/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/30/2018 | | 4/30/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/30/2018 | | 4/30/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/30/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/30/2018 | | DONE |
|
|
|
|