INSP-Final Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 6/4/2018 | 6/4/2018 | 6/4/2018 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areeas marked "ok" where piping can be covered. I noted a missing lateral brace on the new main.
|
Plan assigned to (Tim) | 5/2/2018 | | 5/8/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/8/2018 | | 5/8/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/8/2018 | | DONE |
|
|
|
All requirements met
|
Issue and Print Permit | | | 5/8/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/7/2018 | | 5/7/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/7/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/7/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 4/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2018 9:34AM
|