INSP-Final Inspection | 9/5/2018 | 9/5/2018 | 9/5/2018 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work complete.
|
Issue and Print Permit | | | 8/7/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 8/2/2018 | | 8/3/2018 | | PASS |
Lee G Meredith
|
|
|
Plans approved as noted on drawings.
|
PLANS TAKEN FRONT DESK ALARM | | | 8/3/2018 | | DONE |
|
|
|
Plans approved with review comments and drawing notes.
|
Permit Ready to Issue | | | 8/3/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/2/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 5/17/2018 | | DONE |
|
|
|
Ken emailed to indicate resubmittals have been delayed because the architect and owner are making some changes that have not been completed yet.
|
Plan assigned to (Lee) | 5/1/2018 | | 5/1/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/1/2018 | | FAIL |
|
|
|
Failed prescreen review. Needs engineer of record review and approval. Returned to Ken.
|
Application received | | | 4/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2018 8:45PM
|