Case Summary | | | 5/1/2019 | | DONE |
|
|
|
|
INSP-Supply line flush | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | DONE |
Jim Page
|
|
|
Underground main supply flush complete.
Please call Chris Felty thank you Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Underground rough in Please call James Mair.
Thank you Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
Intake Approval | | | 6/13/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/13/2018 | | 6/13/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/13/2018 | | 6/13/2018 | | PASS |
Tim Frost
|
|
|
|
1st review completed | | | 6/13/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/13/2018 | | DONE |
|
|
|
All requirement met
|
Issue and Print Permit | | | 6/13/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/6/2018 | | DONE |
|
|
|
letter was brought in for Jason Blais-stamped it-attached it to docs and took to Jason B
|
Miscellaneous action | | | 5/14/2018 | | DONE |
|
|
|
Sent the following email.
Clarence,
This is what needs to happen before I can approve and changes to the fire protection including the underground.
• Stock Construction needs to submit an upgrade agreement to make the system compliant in one year. This would include achieving the correct density based on the commodity/hazard.
• The unsprinklered areas would have to be sprinklered immediately including the spray paint booth.
• An impairment plan needs to be submitted and approved for the underground modification. This would include a fire watch while the sprinkler system is was impaired.
Feel free to contact me with questions.
|
Application received | | | 5/8/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2018 12:23PM
|
Agreement of Future work | 6/4/2018 | 6/4/2019 | | | |
Adele J Schaffeld-Griffin
|
|
|
(STOCK CONSTRUCTION) see upgrade agreement attached for fire sprinkler upgrade
|