INSP-Final Inspection | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Rick Phone #: ###-####
|
INSP-Final Inspection | 9/25/2018 | 9/26/2018 | 9/26/2018 | A | PART |
Troy Cobbley
|
|
|
Inspection should actually be a rough-in. See the city approved plans for piping at locations marked "ok" in red that is ok for cover. Project is phased.
terry nelson Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Final Inspection | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | FAIL |
Troy Cobbley
|
|
|
no approved plans or small documents
terry nelson Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
Application received | | | 5/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2018 6:52AM
|
Intake Approval | | | 5/9/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/9/2018 | | 5/9/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/9/2018 | | 5/9/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/9/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/9/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/9/2018 | | DONE |
|
|
|
|