Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR18-00411
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3030 S OWYHEE ST
Project NameOwyhee 24-Plex # 3030
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting a three story (24) plex with a NFPA 13 R system. The system has floor level control valves and utilizes CPVC piping. The 4” underground piping supplies a 2” backflow preventer and header. The system has 2” mains with 1” branch lines.
• The underground piping is under permit FIR18-00013
• The foundation is under permit BLD17-02477
Plan Mod #1 – 8/16/2018
• Piping to the dry sidewall was re-routed.
• The FDC location was moved about 10.-0 on the same wall.
• Additional 90° Elbows were added in the calculations for the 2. pipe that goes underneath of the breezeway to accommodate actual installation.
• The pipe layout was changed on the end units.
• Some rooms that originally had 2 sprinklers heads were changed to now only have 1 sprinkler head.
• All new hydraulic calculations are provided.
[BLD17-02478]
(OWYHEE PARK APARTMENTS) Bldg 2 (101-108, 201-208, 301-308) THERE ARE TWO PERMITS ASSOCIATED WITH THIS E-PLAN. Permit for the construction of a new 27,135 sq. ft., 3 story 24 unit, wood framed apartment building with 8 units per story per the approved plans. Utilities and Drainage approved under GRD17-00010. Project approved under PUD16-00028 & DRH16-00444. This building is fully fire sprinklered with a NFPA 13r system for story increase. CDM
Alternative Materials and Methods:
• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/18/20189/19/20189/19/2018PPASS
DetailsTim Frost
Phone #: ###-#### >> Inspection requested via web by Stan Beus

__________________
Ok on the units I checked, Troy checked the rest.
DOC - Permit Finaled  9/19/2018 PASS
DetailsTim Frost
INSP-Final Inspection9/17/20189/18/20189/18/2018PFAIL
DetailsTim Frost
Phone #: ###-#### >> Inspection requested via web by Stan Beus

_________________
Four lights too close to the sprinklers units 205, 205 and two in 202/
Miscellaneous action  9/18/2018 DONE
emailed Cam to request outstanding test papers noted in Troy's final inspection activity notes.
INSP-Final Inspection8/29/20188/30/20188/30/2018APART
DetailsTroy Cobbley
Sprinkler work complete in the 07's and 08 apartments (south end). Tampers and flow switches tested. Need test papers.


Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection8/28/20188/29/20188/29/2018ACANC
DetailsTroy Cobbley
Could not perform this inspection due to fire alarm issues.


partial final Phone #: ###-#### Inspection requested via web by Stan Beus
CHANGE STATUS TO (ISS)  8/17/2018 DONE
plan mod fees piad-attached new permit to e plan
(F) Reprint permit  8/17/2018 DONE
INSP-Sprinkler Rough-in/Hydro8/15/20188/16/20188/16/2018APASS
DetailsTroy Cobbley
overhead Hydro for the 1st, 2nd, 3rd and FDC passed.

Phone #: ###-#### Inspection requested via web by Stan Beus
Permit Ready to Issue  8/16/2018 DONE
PLAN MOD
Intake Approval  8/16/2018 PASS
Plan Modification Accepted  8/16/2018 DONE
Sprinkler Plan Check8/16/2018 8/16/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  8/16/2018 DONE
INSP-Sprinkler Rough-in8/1/20188/2/20188/2/2018APASS
DetailsJim Page
Rough to cover inspection for soffits on levels 1 and 2 north side complete, approved for cover.

Full RTC Soffits Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/10/20187/11/20187/11/2018APASS
DetailsTroy Cobbley
Sprinkler pendant spacing off from the drop ceilings/soffits in the rooms was verified in the first ans second floor apartments in the south half of the building.

Soffits Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro7/9/20187/9/20187/10/2018PPART
DetailsTroy Cobbley
The preliminary hydro test for the 1st, 2nd and 3rd floors passed. Another overhead hydro will be required when the drops have been cut.
INSP-Sprinkler Rough-in6/19/20186/20/20186/20/2018PPASS
DetailsTroy Cobbley
The piping in rooma 103, 104, 203, 204, 303, 304 is ok to cover. Two dry sidewalls still need to be installed and a cap put on the vertical shaft that the supply piping is in.

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/18/20186/19/20186/19/2018PCANC
DetailsTroy Cobbley
To be rescheduled for tomorrow morning.

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush6/18/20186/19/20186/19/2018PPASS
DetailsTroy Cobbley
The main underground supply line flush and the three breeze way supply flushes passed.

Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/15/20186/18/20186/18/2018PCANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Supply line flush6/15/20186/18/20186/18/2018PCANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in6/13/20186/15/20186/15/2018PCANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Supply line flush6/13/20186/15/20186/14/2018ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in6/4/20186/5/20186/5/2018PPASS
DetailsTroy Cobbley
The piping in apartments 105, 205, 305, 106, 206 306 is ok for cover.

Robert Chambers is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/4/20186/5/20186/4/2018ACANC
DetailsTroy Cobbley
Robert Chambers is the contact for the rough-in for the 24-plex. Thank you. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in6/1/20186/4/20186/4/2018PCANC
DetailsTroy Cobbley
Tenting is not done yet. To be rescheduled for tomorrow afternoon per Colton.

Colton Cox is the contact for this inspection. He is requesting a rough-in for the next 6 units. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/23/20185/29/20185/30/2018PPASS
DetailsTroy Cobbley
Rough-in passed for Units 107, 207, 307, 108, 208, 308. A plan mod will be needed showing the changes in the remote area and pipe routing changes in the other Units.

Colton Cox is the contact for this rough-in on 6 units. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
Intake Approval  5/17/2018 PASS
Plan assigned to (Tim)5/17/2018 5/17/2018 DONE
DetailsTim Frost
Sprinkler Plan Check5/17/2018 5/17/2018 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  5/17/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  5/17/2018 DONE
DetailsTim Frost
Permit Ready to Issue  5/17/2018 DONE
Issue and Print Permit  5/17/2018 DONE
Application received  5/16/2018 DONE
Application submitted via PDS Online on May 16 2018 11:55AM