INSP-Final Inspection | 10/1/2018 | 10/1/2018 | 10/1/2018 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2018 | 10/1/2018 | 10/1/2018 | A | CANC |
Jim Page
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/1/2018 | | DONE |
|
|
|
per Jim Page, reopen permit
|
INSP-Alarm Testing | 9/13/2018 | 9/13/2018 | 9/13/2018 | P | PASS |
Lee G Meredith
|
|
|
|
DOC - Permit Finaled | | | 9/13/2018 | | DONE |
|
|
|
System passed inspection all required documents provided.
|
Fees Due Hold | 6/18/2018 | | 6/18/2018 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 5/24/2018 | | 5/24/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/24/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 5/24/2018 | | 5/24/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/24/2018 | | DONE |
|
|
|
On site review approved.
|
Permit Ready to Issue | | | 5/24/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/24/2018 | | DONE |
|
|
|
|
Application received | | | 5/18/2018 | | DONE |
Lee G Meredith
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 5/18/2018 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
INSP-Final Inspection | 9/12/2018 | 9/13/2018 | | A | |
Jim Page
|
|
|
Please call 1/2 hour before arriving. Thanks Phone #: ###-#### >> Inspection requested via web by david davis
|