INSP-Final Inspection | 7/11/2019 | 7/12/2019 | 7/12/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Josh Eaton is the contact for this final inspection. We appreciate your help with this. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 7/10/2019 | 7/12/2019 | 7/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Conference | 6/11/2019 | 6/12/2019 | 6/12/2019 | P | DONE |
Jim Page
|
|
|
Per conversation with Ron Johnson, the material that Petra wants to move in needs to be non-combustible material, due to fire sprinklers not being monitored/active then material cannot be combustible. Moving in combustibles that are not associated with cunstruction is fuel loading and per Ron Johnson with Boise Fire this is not acceptable until active fire protection is in place.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2019 | 5/23/2019 | 5/23/2019 | A | PASS |
Troy Cobbley
|
|
|
First floor hydro test was witnessed with no visible loss.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
The first floor overhead hydro test failed due to visible loss on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2019 | 5/21/2019 | 5/21/2019 | A | PASS |
Troy Cobbley
|
|
|
The 2nd floor overhead hydro test was witnessed with no loss of pressure.
|
INSP-Sprinkler Rough-in/Hydro | 5/16/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining overhead fire sprinkler piping complete, all areas approved for cover. Hydrostatic test to be completed at a later date.
James Wells is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | PASS |
Troy Cobbley
|
|
|
The rough-in is for 2 heads in the main west entrance hard lid passed. Piping can be covered. The contact says this can take place anytime today (5/2) or tomorrow (5/3). Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where sprinkler piping can be covered. Noted several areas with deficiencies that will need to be addressed such as blocked heads and missing heads.
Jon Beazer is the contact. This is to be a partial rough-in. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/6/2019 | 3/7/2019 | 3/7/2019 | A | PASS |
Troy Cobbley
|
|
|
First floor concealed spaces have been filled with insulation. They can now be covered.
|
INSP-Sprinkler Rough-in | 2/13/2019 | 2/14/2019 | 2/14/2019 | A | PASS |
Troy Cobbley
|
|
|
The south lobby is ok for cover. The hardlid ceiling just inside of the main west facing lobby is ok for cover. Missing earthquake bracing on te mains has been provided except in garage area which needs to be verified for weight as discussed. Sprinkler coverage has been provided under the stairs. It appears that the wall layout on the upper level does not match the sprinkler plans and will need to be modified
Josh Eaton is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan assigned to (Stumbaugh) | 1/31/2019 | | 2/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
plan mod-BLH put it e plan
|
Intake Approval | | | 2/1/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 2/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/1/2019 | | 2/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/1/2019 | | 2/1/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/1/2019 | | DONE |
|
|
|
no plan fee as per Mark
|
Meeting | | | 1/31/2019 | | DONE |
|
|
|
Per Mark Stumbaugh start work flow in eplan. see email in documents
|
Plan Modification Accepted | | | 1/31/2019 | | DONE |
|
|
|
plan mod accepted-per Mark Stumbaugh
|
INSP-Sprinkler Rough-in | 1/16/2019 | 1/17/2019 | 1/17/2019 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the remaining building except for the canopies and the garage/risers. As per the previous inspection branchline restraints are missing and additional 90's have been added that need to be included in on the hydraulic calculations. Piping above the hardlids in the Hospital portion of the building is ok for cover. Wall in the other portions of the building are ok to be covered as long as it does not cover any concealed pockets. There is stil the issue of the Concealed Space sprinkler heads on the second floor that need resolved.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/15/2019 | 1/16/2019 | 1/16/2019 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the north half, first floor, of the building. I noted that not all of the additional 90's have been shown on the drawings or probably provided in the hydraulic calculations. I noted branchline restraints, earthquake bracing, and retaining straps are missing in most locations. It appears sprinkler protection will need to be added under the stairs east of the elevator. Also wood walls have been built in the non-combustible portion of the building and will need to be addressed as discussed. Plan mods will be needed for the added fittings to verify calculations. Combustible concealed spaces have not been addressed. No piping can be covered.
Josh Eaton is the contact for this RTC inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
CHANGE STATUS TO (ISS) | | | 1/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/30/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/30/2018 | | 10/30/2018 | | DONE |
Tim Frost
|
|
|
|
Plan Modification Accepted | | | 10/30/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/30/2018 | | 10/30/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/30/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
INSP-Conference | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | DONE |
Troy Cobbley
|
|
|
Tom and I discussed items that needed corrected.
|
INSP-Sprinkler Rough-in | 10/12/2018 | 10/15/2018 | 10/15/2018 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was more of a conference. I went over issues such as combustible concealed spaces, sprinkler obstructions, missinge branchline restraints, missing earth quake bracing, missing upright protection. Basically we all agreed the plans need to be resubmitted showing all of the additional heads, additional piping, rerouted piping, additional fittings. It also appears the CC2 heads may not be able to be used on the second floor. Draft stops has not been installed for the CC2 heads. No approval for cover was given.
|
INSP-Sprinkler Rough-in | 10/2/2018 | 10/3/2018 | 10/3/2018 | P | FAIL |
Troy Cobbley
|
|
|
There were no city approved plans or documents on site. We did discuss what appears to be alot of blocked heads and combustible concealed spaces that will need addressed.
Richard Clark is the contact for this RTC inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Issue and Print Permit | | | 6/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/11/2018 | | PASS |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 6/11/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/11/2018 | | 6/11/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/11/2018 | | DONE |
|
|
|
all requirements met
|
Intake Approval | | | 6/6/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/6/2018 | | 6/6/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/6/2018 | | 6/6/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/6/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/6/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 5/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 31 2018 10:52AM
|