INSP-Final Inspection | 8/15/2018 | 8/17/2018 | 8/17/2018 | A | PASS |
Jim Page
|
|
|
Previously noted items have been completed, final fire sprinkler inspection complete.
Please call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 8/9/2018 | 8/10/2018 | 8/10/2018 | P | FAIL |
Jim Page
|
|
|
Three heads in clean room are overspace @ 144 square feet, heads need to be relocated to 130 square feet or less. Pass-through section between clean room and hallway requires fire sprinklers to be installed per conversation with Tim Frost Fire sprinkler plan reviewer.
Call Anthony to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 8/9/2018 | 8/10/2018 | 8/10/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for newly installed overhead fire sprinkler piping witnessed, no pressure loss observed at contractor provided gauge.
Call Anthony to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 8/7/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 8/3/2018 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 8/3/2018 | | 8/3/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/3/2018 | | 8/3/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/3/2018 | | DONE |
|
|
|
plan mod please do not issue
|
INSP-Sprinkler Rough-in/Hydro | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | PART |
Troy Cobbley
|
|
|
The rough-in for the mains and branchlines passed. Missing one earthquake brace at the drop down to the clean room. Need as-builts due to two addtional 90's in the 4" feed main just outside of the riser room. Will need another rough to cover inspection when the flex heads are installed. Not able to do the hydro test due to fhe flex heads not being installed.
Call Anthony to coordinate, thanks Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan resubmittals received | | | 6/11/2018 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/11/2018 | | 6/11/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/11/2018 | | 6/11/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/11/2018 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 6/11/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/7/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 6/7/2018 | | 6/7/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/7/2018 | | 6/7/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/7/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/7/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 6/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2018 9:33AM
|