INSP-Final Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Supply line flush | 4/1/2019 | 4/2/2019 | 4/2/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
George Jess is the contact. This inspection is for an underground flush/hydro. Stacey with Suez should already be aware of this inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/2/2019 | 4/2/2019 | 4/2/2019 | A | DONE |
Jim Page
|
|
|
Hyhdrostatic test for undergorund supply witnessed, no pressure loss observed.
|
INSP-Sprinkler Rough-in | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Underground Rough In Phone #: ###-#### Inspection requested via web by Stan Beus
|
Issue and Print Permit | | | 6/22/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/21/2018 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/21/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/21/2018 | | 6/21/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/21/2018 | | DONE |
|
|
|
all requirements met
|
Intake Approval | | | 6/14/2018 | | PASS |
|
|
|
|
Sprinkler Plan Check | 6/14/2018 | | 6/14/2018 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 6/14/2018 | | 6/14/2018 | | DONE |
Tim Frost
|
|
|
|
1st review completed | | | 6/14/2018 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 6/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 12 2018 2:58PM
|