INSP-Final Inspection | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Don Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 | A | PART |
Adele J Schaffeld-Griffin
|
|
|
above grid phase 2, Need As-Builds when project is completed. Don Forester Phone #: ###-#### >> Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in | 11/1/2018 | 11/2/2018 | 11/2/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Don Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/30/2018 | 10/31/2018 | 10/31/2018 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact.
Don Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/12/2018 | 10/12/2018 | 10/12/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
|
Issue and Print Permit | | | 6/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/15/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/15/2018 | | 6/15/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/15/2018 | | 6/15/2018 | | PASS |
Tim Frost
|
|
|
|
1st review completed | | | 6/15/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2018 | | DONE |
Tim Frost
|
|
|
|
Override - Parcel Holds | | | 6/15/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 6/15/2018 | | DONE |
|
|
|
|
Application received | | | 6/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 13 2018 1:56PM
|