Case Summary | | | 11/29/2018 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/18/2018 | 9/18/2018 | 9/18/2018 | P | PASS |
Tim Frost
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball
|
DOC - Permit Finaled | | | 9/18/2018 | | DONE |
Tim Frost
|
|
|
|
INSP-Final Inspection | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | CANC |
Troy Cobbley
|
|
|
Ceiling tile not installed per contractor. To be rescheduled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 7/5/2018 | 7/9/2018 | 7/9/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Intake Approval | | | 6/27/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/27/2018 | | 6/27/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/27/2018 | | 6/27/2018 | | PASS |
Tim Frost
|
|
|
|
1st review completed | | | 6/27/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/27/2018 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 6/27/2018 | | DONE |
|
|
|
|
Application received | | | 6/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 26 2018 12:44PM
|