INSP-Final Inspection | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for undergorund supply witnessed, no pressure loss observed.
this is a underground hydro test. troy is our contact Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for underground supply complete, The IBR, piping from IBR to the PIV and 3 feet past PIV approved for cover. Remaining underground to be installed at a later date.
TROY NELSON IS OUR FOREMAN. THIS IS AN UNDERGROUND COVER INSPECTION. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
Application received | | | 6/28/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 28 2018 7:43AM
|
Intake Approval | | | 6/28/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/28/2018 | | 6/28/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/28/2018 | | 6/28/2018 | | PASS |
Tim Frost
|
|
|
|
1st review completed | | | 6/28/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/28/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/28/2018 | | DONE |
|
|
|
|