INSP-Final Inspection | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Mark Scharfen
|
|
|
Fully tested fire sprinkler panel, cell dialer, verified signals, 100% functional. Passed finel.
Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
|
INSP-Sprinkler Rough-in | 4/1/2019 | 4/1/2019 | 4/1/2019 | A | PASS |
Jim Page
|
|
|
Insulation inspection for fire sprinkler piping heat trace complete, approved for cover.
|
INSP-Conference | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | CANC |
Jim Page
|
|
|
Inspection is for a rough in for heat trace insulation cover, not a conference, this request is cancelled.
Phone #: 2085733237 >> Inspection requested via mobile web by Scott wilson
|
Issue and Print Permit | | | 7/9/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 7/3/2018 | | 7/5/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 7/5/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 7/3/2018 | | 7/5/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/5/2018 | | DONE |
|
|
|
Plans approved with review comments.
|
Miscellaneous action | | | 7/5/2018 | | DONE |
|
|
|
The address shown on the drawings and documents is incorrect. Sheri was notified that this is required to be corrected on as built drawings prior to acceptance testing. I also informed her that the communicator on the riser drawing indicates that IP configuration may be used. If so, battery back up for all related equipment is required.
|
Permit Ready to Issue | | | 7/5/2018 | | DONE |
|
|
|
|
Application received | | | 7/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 3 2018 1:53PM
|