Skyline Apartments Bldg C - New Building Fire Alarm. This work is associated with building permit BLD17094625 and project PRJ18-04367. Address is 2090 S hudson Ave.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/2/20195/3/20195/3/2019PPASS
DetailsMark Scharfen
Fully tested fire sprinkler panel, cell dialer, verified signals, 100% functional. Passed finel.

Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
INSP-Sprinkler Rough-in4/1/20194/1/20194/1/2019APASS
DetailsJim Page
Insulation inspection for fire sprinkler piping heat trace complete, approved for cover.
INSP-Conference4/1/20194/1/20194/1/2019PCANC
DetailsJim Page
Inspection is for a rough in for heat trace insulation cover, not a conference, this request is cancelled.

Phone #: 2085733237 >> Inspection requested via mobile web by Scott wilson
Issue and Print Permit  7/9/2018 DONE
Plan assigned to (Lee)7/3/2018 7/5/2018 DONE
DetailsLee G Meredith
1st review completed  7/5/2018 PASS
Alarm Plan Check7/3/2018 7/5/2018 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  7/5/2018 DONE
Plans approved with review comments.
Miscellaneous action  7/5/2018 DONE
The address shown on the drawings and documents is incorrect. Sheri was notified that this is required to be corrected on as built drawings prior to acceptance testing. I also informed her that the communicator on the riser drawing indicates that IP configuration may be used. If so, battery back up for all related equipment is required.
Permit Ready to Issue  7/5/2018 DONE
Application received  7/3/2018 DONE
Application submitted via PDS Online on Jul 3 2018 1:53PM