INSP-Final Inspection | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | CANC |
Troy Cobbley
|
|
|
Not ready per Nathan and will be rescheduled.
Call prior to going Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
INSP-Conference | 12/6/2018 | 12/6/2018 | 12/6/2018 | P | DONE |
Troy Cobbley
|
|
|
Went over strobe spacing with the electrian. I noted several strobes that will need to be relocated or increased candella. I'm questioning the placement and function of smoke detector 81 in the Gymnasium.
|
INSP-Alarm Testing | 11/21/2018 | 11/21/2018 | 11/21/2018 | P | DONE |
Troy Cobbley
|
|
|
The low air switch has been replaced and tested. The strobe in Room 9 has been replaced and tested. The fire alarm system in the existing school is complete except for some of the doors do not swing shut when the door mag released. To final project the doors will need to be addressed, as-builts and the new portion of the school will need to be completed.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
INSP-Alarm Testing | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | DONE |
Troy Cobbley
|
|
|
Today we tested the interconnection of the existing fire alarm devices with the new panel. All devices on the existing risers functioned except the "low air" pressure switch on the System #1 did not function. It will need to be replaced asap as discussed.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Plan Modification Accepted | | | 11/20/2018 | | DONE |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 11/19/2018 | | 11/20/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/20/2018 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 11/20/2018 | | DONE |
|
|
|
Plan Mod Approved
|
CHANGE STATUS TO (ISS) | | | 11/20/2018 | | DONE |
|
|
|
|
INSP-Alarm Testing | 11/19/2018 | 11/19/2018 | 11/19/2018 | A | DONE |
Troy Cobbley
|
|
|
We tested the smoke detectors and notification devices today. All functioned except for the strobe in the back of Room 9. I also noted several doors that did not swing shut when the door mags released.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
INSP-Alarm Testing | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | DONE |
Troy Cobbley
|
|
|
For todays inspection I only verified device locations. I noted smoke detectors needing centered on the door on the classroom side. Per a later phone call from Lee these detectors are ok to be deleted as long as the distance from the header to the ceiling does not exceed 24". I also noted many strobes that are overspaced in nearly every classroom and atleast one in the main corridor. I noted that the communication means being used is not what is shown on the approved plans. As-builts will be required but possibly for plan mods.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Miscellaneous action | | | 11/16/2018 | | DONE |
|
|
|
As built drawings showing classroom detectors have been removed. Measurments to be verified by the inspector. Candela has been increased where strobes were moved. All appears acceptable, subject to inspection.
|
Miscellaneous action | | | 10/16/2018 | | DONE |
|
|
|
Sheri Carlson requested the work flow be re-opened so a plan modification can be submitted.
|
Miscellaneous action | | | 10/16/2018 | | DONE |
|
|
|
Nathan emailed to indicate the originally planned panel is no longer in production and will be replaced with a Silent Knight 6820XL-EVS. I informed him that as built drawings and calculations will be required at the completion of the project that indicates the changes.
|
Plan Modification Accepted | | | 10/16/2018 | | DONE |
|
|
|
|
1st review completed | | | 10/16/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 10/16/2018 | | 10/16/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/16/2018 | | DONE |
|
|
|
Plan modification approved with revised review comments.
|
Permit Ready to Issue | | | 10/16/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/16/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/16/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/2/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 10/2/2018 | | 10/2/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/2/2018 | | DONE |
|
|
|
Plan mod approved with review comments.
|
Permit Ready to Issue | | | 10/2/2018 | | DONE |
|
|
|
plan mod do not re issue
|
CHANGE STATUS TO (ISS) | | | 10/2/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/2/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 10/1/2018 | | DONE |
|
|
|
Sheri requested the work flow be opened for a plan modification that includes adding detection for fire smoke damper control and moving notification from the walls to the ceiling.
|
Plan resubmittals received | | | 8/3/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 8/3/2018 | | 8/3/2018 | | DONE |
Lee G Meredith
|
|
|
Resubmittal plans approved as noted.
|
PLANS TAKEN FRONT DESK ALARM | | | 8/3/2018 | | DONE |
|
|
|
Plans approved with review comments and inspectors drawing notes.
|
Permit Ready to Issue | | | 8/3/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/3/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 7/24/2018 | | DONE |
|
|
|
Drawings failed review and were returned to Sheri with changemarks on floor plans. Drawings are to be corrected and resubmitted.
|
Plan assigned to (Lee) | 7/23/2018 | | 7/23/2018 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 7/23/2018 | | DONE |
|
|
|
Some classroom walls appear to be blocking the strobe. I emailed charlie to have him verify the height of the walls to determine actual requirements.
7/24/18 Charlie responded to say the walls are full height and that they will need to add strobes. Plans to be returned for corrections.
|
Application received | | | 7/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2018 9:26AM
|