Permit Information
Permit NumberFIR18-00595
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 5656 W MORRIS HILL RD
Project NameMorris Hill Paint Booth
Customer Number 
ePlanReviewYes
Description
[Boise Mobile Equipment BME - Paint Booth]
The fire sprinkler scope of work consists of protecting a spray. A new riser is being added to the riser manifold. The system has 6” mains and 2” Lines

[BLD18-01915]
The fire sprinkler system is used for building area increase and for fire area. To construct a new 12-foot-wide opening at grade level in the existing North exterior wall of an existing building (48,000 square feet 1st story and about 5,200 square feet 2nd story) to accommodate a new 12’ x 12’ overhead door. Work includes steel columns, steel beams, a steel box beam, and a new overhead door having a minimum R-4.75 insulation value. To construct two adjacent rooms on the grade level (597 square feet and 105 square feet) with ceilings above the new rooms. Work is to include steel columns, steel wide flange beams, 6” ceiling joists at 16” on center, 5/8 inch “Type X” gypsum board installed as a ceiling, hat channels and gypsum board installed on the inside of the existing exterior walls, steel stud and gypsum board bearing and non-bearing walls, and new interior doors. The ceiling will be about 15 feet 5 inches above the floor for the larger room and about 8 feet above the floor for the smaller room. The larger room will be served by the new overhead door and will be used for storage. The smaller room will be used for paint mixing and storage. The area above the new room is not approved for occupancy since the live load capacity is only 20 pounds per square foot. A floor deck is not allowed to be installed above the ceiling joists. An existing stairway located next to the larger new storage room serves an existing mezzanine. The stairway will be maintained with new handrails added on each side and a guard provided to prevent falls onto the new ceiling. Special Inspection is required for welding and for anchors post-installed in hardened masonry and/or concrete. To convert a second story storage room to a 768 square foot open office. Work is to include three 2’ tall by 4’ wide exterior windows, steel stud and gypsum board furred walls, a suspended acoustical ceiling, a new steel stud and gypsum board guard, a new door with glass sidelight, carpet, and finishes. To install a prefabricated 704 square foot spray booth (based on interior dimensions) with a 16 foot tall ceiling on the 1st story. The spray booth is required to comply with its listing and with the 2015 International Fire Code. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  11/20/2019 DONE
Test & asbuilt passed. Added DOC_Finaled.
Permit Ready to Issue  3/11/2019 DONE
met
CHANGE STATUS TO (ISS)  3/11/2019 DONE
Miscellaneous action  3/8/2019 PASS
DetailsMark Stumbaugh
As Built Drawings received
Sprinkler Plan Check2/27/2019 2/28/2019 FAIL
DetailsMark Stumbaugh
Corrections needed
PLANS/APPL TAKEN TO FRONT DESK  2/28/2019 DONE
DetailsMark Stumbaugh
Plan Modification Accepted  2/27/2019 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)2/27/2019 2/27/2019 DONE
DetailsMark Stumbaugh
INSP-Final Inspection10/11/201810/12/201810/12/2018APASS
DetailsTroy Cobbley
Permit finaled. As-builts showing the high temp heads and deleted ready riser to be provided.

Roy Phone #: ###-####
INSP-Sprinkler Rough-in9/6/20189/6/20189/6/2018PPASS
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping associated with paint booth complete.
INSP-Sprinkler Rough-in/Hydro9/5/20189/6/20189/6/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping protecting new paint booth witnessed, no pressure loss observed at riser provided gauge.

Robert Mullins is Foreman on site. Phone #: ###-#### Inspection requested via web by Brett Lawatch
Sprinkler Plan Check8/14/2018 8/14/2018 PASS
DetailsTim Frost
Please, see attached comments.
Plan resubmittals received  8/14/2018 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/14/2018 DONE
DetailsTim Frost
Permit Ready to Issue  8/14/2018 DONE
all requirements met
Issue and Print Permit  8/14/2018 DONE
Sprinkler Plan Check7/30/2018 8/1/2018 FAIL
DetailsTim Frost
1st review completed  8/1/2018 FAIL
DetailsTim Frost
Miscellaneous action  8/1/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Plan assigned to (Tim)7/30/2018 7/30/2018 DONE
DetailsTim Frost
Intake Approval  7/30/2018 PASS
Application received  7/26/2018 DONE
Application submitted via PDS Online on Jul 26 2018 9:24AM