INSP-Final Inspection | 10/17/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/1/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover. Fire sprinkler head in west cooler in main kitchen has head to far off of wall, fire sprinkler head in cooler will need to be relocated, will verify reloaction at final inspection.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping for head in lower obstruction that was over 48 inches complete, approved for cover.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/9/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.
Tom Phone #: ###-####
|
Intake Approval | | | 8/1/2018 | | PASS |
|
|
|
|
Sprinkler Plan Check | 8/1/2018 | | 8/1/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 8/1/2018 | | 8/1/2018 | | DONE |
Tim Frost
|
|
|
|
1st review completed | | | 8/1/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/1/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/1/2018 | | DONE |
|
|
|
|
Application received | | | 7/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 30 2018 10:52AM
|