INSP-Final Inspection | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Call half hour before to meet // Garrett Phone #: ###-####
|
Intake Approval | | | 9/24/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 9/24/2018 | | 9/24/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/24/2018 | | 9/24/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/24/2018 | | DONE |
|
|
|
Plan Mod Approved
|
CHANGE STATUS TO (ISS) | | | 9/24/2018 | | DONE |
|
|
|
no fee for plan mod/as built per Tim F.
|
(F) Reprint permit | | | 9/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/27/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (Adele) | 8/27/2018 | | 8/27/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Sprinkler Plan Check | 8/27/2018 | | 8/27/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 8/27/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/27/2018 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 8/27/2018 | | DONE |
|
|
|
|
Application received | | | 8/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2018 11:06AM
|