INSP-Final Inspection | 5/1/2020 | 5/5/2020 | 5/6/2020 | P | CANC |
Troy Cobbley
|
|
|
please come after 2:30 if possible. this is for the forward flow for the new BFP. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Final Inspection | 5/4/2020 | 5/6/2020 | 5/6/2020 | A | PASS |
Troy Cobbley
|
|
|
Forward flow test witnessed. Permit finaled. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Final Inspection | 3/16/2020 | 3/18/2020 | 3/17/2020 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Jim.
needs backflow forward flow test. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Final Inspection | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | CANC |
Troy Cobbley
|
|
|
Cancel per contact.
Forward Flow and Final Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Final Inspection | 12/17/2019 | 12/18/2019 | 12/18/2019 | P | CANC |
Troy Cobbley
|
|
|
Cancel per contact. last item, forward flow test Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Final Inspection | 12/16/2019 | 12/17/2019 | 12/17/2019 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Troy Cobbley
|
|
|
Hydro test passed and interconnection with the fire alarm panel passed. Need hydraulic sticker and forward flush passed to be finaled.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Sprinkler Rough-in/Hydro | 3/7/2019 | 3/8/2019 | 3/8/2019 | P | PASS |
Troy Cobbley
|
|
|
Under ground Hydro test witnessed with no visible loss at the guage.
Jim Danes Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Supply line flush | 3/5/2019 | 3/7/2019 | 3/7/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush passed.
|
Issue and Print Permit | | | 1/24/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/11/2019 | | 1/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/14/2019 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 1/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/11/2019 | | 1/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 8/9/2018 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/9/2018 | | 8/9/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/9/2018 | | 8/9/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/9/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/9/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 8/8/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 8 2018 5:13PM
|