INSP-Final Inspection | 4/6/2019 | 4/8/2019 | 4/8/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire alarm inspection complete.
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
INSP-Final Inspection | 2/13/2019 | 2/14/2019 | 2/14/2019 | A | FAIL |
Troy Cobbley
|
|
|
The hvac units did not shut down upon alarm activation as required per IMC 606.4, need the enclosure for the communicator installed.
As early as possible Phone #: 2088308262 >> Inspection requested via mobile web by Tip Ioane
|
FIR-Aging Inspection | 2/13/2019 | 2/13/2019 | 2/13/2019 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final due to issues with hvac activation, need protecive cover for IP DACT, need cut sheet for FACP showing internal mounting for IP DACT, need fuel verification for generator, need to verify as-builts are correct (NAC's)
|
INSP-Final Inspection | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | CANC |
Troy Cobbley
|
|
|
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price Inspection cancelled via mobile web on Wednesday, February 13, 2019.
|
Plan Modification Accepted | | | 2/12/2019 | | DONE |
|
|
|
plan mod request via email. Eplan work flow started.
|
Plan assigned to (Lee) | 2/12/2019 | | 2/12/2019 | | DONE |
Lee G Meredith
|
|
|
As built drawing showing IP communicator.
|
Alarm Plan Check | 2/12/2019 | | 2/12/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/12/2019 | | DONE |
|
|
|
Plan passed. No additional review comments.
|
Permit Ready to Issue | | | 2/12/2019 | | DONE |
|
|
|
plan mod approval
|
CHANGE STATUS TO (ISS) | | | 2/12/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 2/4/2019 | 2/7/2019 | 2/7/2019 | A | CANC |
Troy Cobbley
|
|
|
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
INSP-Final Inspection | 1/24/2019 | 1/31/2019 | 1/31/2019 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection included verifying candellas for the audio/visuals, fire sprinkler risers and smoke detector door release. We were unable to test hvac shutdown due to Target Policy. Plan modifications are required showing the changes strobes, NAC panels, addressing and means of communication. Note IP DACT is installed inproperly and not shown on the plans or battery calcs.
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Permit Ready to Issue | | | 1/29/2019 | | DONE |
|
|
|
plan mod approval
|
CHANGE STATUS TO (ISS) | | | 1/29/2019 | | |
|
|
|
|
Miscellaneous action | | | 1/28/2019 | | DONE |
|
|
|
Shari requested the work flow be opened for a plan modification.
|
Plan Modification Accepted | | | 1/28/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 1/28/2019 | | 1/28/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/28/2019 | | DONE |
|
|
|
Plan mod approved. No additional review comments.
|
INSP-Final Inspection | 1/21/2019 | 1/24/2019 | 1/24/2019 | A | DONE |
Troy Cobbley
|
|
|
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price.
3:30 pm test is too late for Target. Nathan cancelled.
|
INSP-Final Inspection | 1/21/2019 | 1/22/2019 | 1/21/2019 | A | CANC |
Troy Cobbley
|
|
|
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price Inspection cancelled via mobile web on Monday, January 21, 2019.
|
INSP-Final Inspection | 11/26/2018 | 11/27/2018 | 11/27/2018 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was just for the notification devices. See the city approved plans for the devices overspaced or mounted too high. Not all of the devices have been checked for the correct candella. Contractor will need to contact plan review on whether a plan mod is needed or just as-builts. Also the fire doors did not close when the smoke detectors were tested.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Miscellaneous action | | | 10/16/2018 | | DONE |
|
|
|
Sheri Carlson requested the work flow be re-opened so a plan modification can be submitted.
|
Plan Modification Accepted | | | 10/16/2018 | | DONE |
|
|
|
|
1st review completed | | | 10/16/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 10/16/2018 | | 10/16/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/16/2018 | | DONE |
|
|
|
Plan modification approved. No additional review comments provided.
|
Permit Ready to Issue | | | 10/16/2018 | | DONE |
|
|
|
Plan Mod Approved
|
CHANGE STATUS TO (ISS) | | | 10/16/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/16/2018 | | DONE |
|
|
|
|
INSP-Conference | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | DONE |
Troy Cobbley
|
|
|
We dicussed obstructions to the strobes in the Store Room areas.
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
PLANS TAKEN FRONT DESK ALARM | | | 8/17/2018 | | DONE |
|
|
|
Plans approved with review comments and noted requirements on drawings.
|
Permit Ready to Issue | | | 8/17/2018 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 8/17/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 8/16/2018 | | DONE |
|
|
|
Approval is pending on confirmation by contractor of all ceiling heights.
|
Plan assigned to (Lee) | 8/14/2018 | | 8/15/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 8/15/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 8/14/2018 | | 8/15/2018 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 8/14/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 14 2018 2:16PM
|