INSP-Final Inspection | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Call Anthony when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | CANC |
Jim Page
|
|
|
Irrigation timers are not hooked up to the zone solenoids, inspection cancelled per conversation with point of contact, will be rescheduled for a later date.
Call Alicia before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | CANC |
Troy Cobbley
|
|
|
Went to project but it was not ready.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 12/18/2018 | 12/19/2018 | 12/19/2018 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PASS |
Jim Page
|
|
|
Tenting inspection complete, cover approved for overhead fire sprinkler piping.
Tenting inspection. Please let Anthony know if there are any issues. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 9/27/2018 | 9/27/2018 | 9/27/2018 | A | PART |
Jim Page
|
|
|
Rough in inspection complete for overhead fire sprinkler piping, tenting to be installed at a later date, cover is not approved until tenting inspection is complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete.
Doesn’t have to be PM, we will be ready this morning. Call Anthony to coordinate, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 9/26/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/26/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/25/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 9/25/2018 | | 9/25/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/25/2018 | | 9/25/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/25/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/25/2018 | | DONE |
|
|
|
|
Application received | | | 9/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2018 12:49PM
|