Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR18-00738
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 8000 S FEDERAL WAY
Project NameMICRON B22 B25 TRESTLE RELO UG
Customer Number 
ePlanReviewYes
Description
[Micron Building 25 Trestle Reroute Underground] - Quick Permit
Relocate an existing 10" main fire loop pipe and an 8" fire sprinkler service as needed for the new trestle foundation. Fire services must be placed back in service at end of day. Install all new piping first then do the tie ins as necessary.

There does not seem to be an associated building permit at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/8/201811/9/201811/9/2018APASS
DetailsJim Page
Final inspection for scope of work complete.

Please call Troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in/Hydro11/9/201811/9/201811/9/2018ADONE
DetailsJim Page
Hydrostatic test for underground supply re-route witnessed, no pressure loss observed.
INSP-Sprinkler Rough-in/Hydro11/5/201811/6/201811/6/2018PCANC
DetailsTroy Cobbley
UG Hydro for 8" service. Please call Troy With time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in/Hydro11/5/201811/5/201811/5/2018PCANC
DetailsTroy Cobbley
Scheduled for the wrong day.

Hydro Test for 8" UG.

Please call Troy with time frame. Thanks Phone #: ###-#### Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in/Hydro11/2/201811/5/201811/5/2018ACANC
DetailsJim Page
UG Cover/Hydro Troy Phone #: ###-#### >> Inspection requested via web by Nathan Stenquist Inspection cancelled from web by: Nathan Stenquist
INSP-Supply line flush10/22/201810/22/201810/22/2018PDONE
DetailsJim Page
Undergound main line flush witnessed and is complete.
INSP-Sprinkler Rough-in/Hydro10/19/201810/22/201810/22/2018PPASS
DetailsJim Page
Rough to cover inspection for underground supply complete, approved for ocver.

UG Hydro Troy Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
INSP-Conference10/17/201810/17/201810/17/2018PDONE
DetailsJim Page
Conference for undergorund supply complete.
INSP-Sprinkler Rough-in10/17/201810/17/201810/17/2018PCANC
DetailsJim Page
Reuqest was for conference, this request is canceeld.

UG Cover Troy Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
Sprinkler Plan Check9/27/2018 9/27/2018 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  9/27/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  9/27/2018 DONE
DetailsTim Frost
Permit Ready to Issue  9/27/2018 DONE
met
Issue and Print Permit  9/27/2018 DONE
Intake Approval  9/26/2018 PASS
DetailsTim Frost
Plan assigned to (Tim)9/26/2018 9/26/2018 DONE
DetailsTim Frost
Application received  9/24/2018 DONE
Application submitted via PDS Online on Sep 24 2018 9:57AM