INSP-Final Inspection | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PASS |
Jim Page
|
|
|
Final inspection for scope of work complete.
Please call Troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 11/9/2018 | 11/9/2018 | 11/9/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply re-route witnessed, no pressure loss observed.
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2018 | 11/6/2018 | 11/6/2018 | P | CANC |
Troy Cobbley
|
|
|
UG Hydro for 8" service. Please call Troy With time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | CANC |
Troy Cobbley
|
|
|
Scheduled for the wrong day.
Hydro Test for 8" UG.
Please call Troy with time frame. Thanks Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | CANC |
Jim Page
|
|
|
UG Cover/Hydro Troy Phone #: ###-#### >> Inspection requested via web by Nathan Stenquist Inspection cancelled from web by: Nathan Stenquist
|
INSP-Supply line flush | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | DONE |
Jim Page
|
|
|
Undergound main line flush witnessed and is complete.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for ocver.
UG Hydro Troy Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Conference | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | DONE |
Jim Page
|
|
|
Conference for undergorund supply complete.
|
INSP-Sprinkler Rough-in | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | CANC |
Jim Page
|
|
|
Reuqest was for conference, this request is canceeld.
UG Cover Troy Nelson Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
Sprinkler Plan Check | 9/27/2018 | | 9/27/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/27/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/27/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 9/27/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/26/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 9/26/2018 | | 9/26/2018 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 9/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 24 2018 9:57AM
|