INSP-Final Inspection | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Troy Cobbley
|
|
|
permit finaled. Hydro test passed
Adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/11/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Troy Cobbley
|
|
|
The rough-in for the new piping passed. Still need the drops for under the doors completed, earthquake bracing completed and the two tie-ins completed.
ADAM IS OUR FOREMAN Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
Intake Approval | | | 10/1/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/1/2018 | | 10/1/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/1/2018 | | 10/1/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/1/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/1/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/1/2018 | | DONE |
|
|
|
|
Application received | | | 9/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2018 9:25AM
|