INSP-Final Inspection | 1/16/2019 | 1/17/2019 | 1/17/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 12/21/2018 | 12/26/2018 | 12/26/2018 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Intake Approval | | | 10/19/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/19/2018 | | 10/19/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/19/2018 | | 10/19/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/19/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/19/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 10/19/2018 | | DONE |
|
|
|
|
Application received | | | 10/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2018 10:41AM
|