Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR18-00801
StatusFinaled
Name JOHNSON CONTROLS FIRE PROTECTION SE
Site Address 711 N CURTIS RD
Project NameSA Rehabilitation Hospital
Customer Number 
ePlanReviewYes
Description
PROVIDE AND INSTALL A NEW AUTOMATIC AND MANUAL FIRE ALARM SYSTEM. This work is associated with building permit BLD18-01425.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/19/20197/22/20197/22/2019APASS
DetailsTroy Cobbley
permit finaled


7am // damion Phone #: ###-####
INSP-Final Inspection7/18/20197/19/20197/19/2019AFAIL
DetailsTroy Cobbley
The interconnection with the kitchen hood has been tested but it was brought to my attention that there is a second, small, hood suppression system that is not ready yet. This small suppression system will need to be tested prior to a final on this permit.

Brandon Phone #: ###-####
INSP-Final Inspection7/17/20197/17/20197/18/2019PFAIL
DetailsTroy Cobbley
All items tested except for the kitchen hood interconnect.

Brandon- Phone #: ###-####
Plan Modification Accepted  7/17/2019 DONE
1st review completed  7/17/2019 PASS
Alarm Plan Check7/17/2019 7/17/2019 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  7/17/2019 DONE
Plan mod passed.
Permit Ready to Issue  7/17/2019 DONE
PLAN MOD
CHANGE STATUS TO (ISS)  7/17/2019 DONE
plan mod
Plan assigned to (Lee)7/16/2019 7/17/2019 FAIL
DetailsLee G Meredith
Correct matrix for CO detector requirement to transmit CO Alarm conditions to monitoring station, as previously noted.
Plan resubmittals received  7/16/2019 DONE
as built requested per Kristen
INSP-Final Inspection7/5/20197/5/20197/5/2019PPART
DetailsTroy Cobbley
Fire alarm panel verified, phone lines verified, batteries verified, interconnection with tamper switches, PIV switch and flow switches verified. Per Lee the CO detectors need to annunciate in the area covered.


Brandon Phone #: ###-####
INSP-Final Inspection7/1/20197/3/20197/3/2019PFAIL
DetailsTroy Cobbley
Inspection was for basics so that furniture could be moved in. After testing devices we found out that the monitoring account was only a test account. All devices will need to be tested again.

Brandon Phone #: ###-####
INSP-Final Inspection6/26/20197/3/20197/3/2019AFAIL
DetailsTroy Cobbley
PIV does not work, outside alarm bell does not work, no buttset to verify phone lines, no small documents. No testing performed.

first inspection of the day // Kristin Phone #: ###-####
Plan resubmittals received  5/1/2019 DONE
Plan assigned to (Lee)5/1/2019 5/1/2019 DONE
DetailsLee G Meredith
1st review completed  5/1/2019 PASS
Alarm Plan Check5/1/2019 5/1/2019 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  5/1/2019 DONE
Passed with reviesed comments.
Permit Ready to Issue  5/1/2019 DONE
Issue and Print Permit  5/1/2019 DONE
Meeting  4/15/2019 DONE
reassigned in eplan review so that Kristin can accept task and make changes
Plan resubmittals received  4/15/2019 DONE
Alarm Plan Check4/15/2019 4/15/2019 FAIL
DetailsLee G Meredith
Corridor and food storage room notification appears to have been adequatly addressed. Kitchen hood still shows fire alarm system interface for control that is not allowed. No other changemarks have been addressed. Returned to applicant for corrections.
Telephone call  4/15/2019 DONE
Called Joe Hobbs - JCI PM to let him know most required correction items have not been addressed and that the drawings have been returned for correction of the remaining items.
Plan assigned to (Lee)10/18/2018 10/22/2018 DONE
DetailsLee G Meredith
1st review completed  10/22/2018 FAIL
See 1st review comments.
Application received  10/18/2018 DONE
Application submitted via PDS Online on Oct 18 2018 12:47PM