Miscellaneous action | | | 1/23/2019 | | DONE |
|
|
|
As built drawings received.
|
INSP-Final Inspection | 1/16/2019 | 1/17/2019 | 1/17/2019 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work complete.
This inspection needs to be between 4 and 5pm. The inspection is being coordinated with the Boise Center on the Grove as well as sprinkler, electrician and us. Our technician that will be at the inspection is Peter Naumov. His number is ###-#### Phone #: ###-#### Inspection requested via web by Cheyenne Zumstein
|
Plan Modification Accepted | | | 1/16/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 1/16/2019 | | 1/16/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/16/2019 | | DONE |
|
|
|
Plan mod review passed. No additional review comments.
|
Permit Ready to Issue | | | 1/16/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 1/16/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/8/2019 | 1/10/2019 | 1/10/2019 | P | FAIL |
Jim Page
|
|
|
Resubmit plans showing new NAC panel. Need to meet sound requirements in discussed areas. Provide calculations for 3rd circuit used.
This inspection is being requested to be done after 1:30pm as they are having to coordinate with the Boise Center on the Grove. Crane Alarm''s technician for this final is Eric Nelson ###-#### Phone #: ###-#### Inspection requested via web by Cheyenne Zumstein
|
Plan assigned to (Lee) | 10/23/2018 | | 10/24/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 10/24/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 10/24/2018 | | 10/24/2018 | | PASS |
Lee G Meredith
|
|
|
|
Permit Ready to Issue | | | 10/24/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 10/24/2018 | | DONE |
|
|
|
|
Application received | | | 10/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2018 5:12PM
|