INSP-Final Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection complete.
|
INSP-Final Inspection | 5/1/2019 | 5/2/2019 | 5/2/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need the interconnection with the fire alarm system tested and balcony ceilings installed. Walk through of the apartments passed..
Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed with anti-freeze, no pressure loss observed at riser gauges.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/8/2019 | 1/9/2019 | 1/9/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/4/2019 | 1/7/2019 | 1/7/2019 | A | PART |
Jim Page
|
|
|
Tentin in Unit B-HC level 3 has been corrected, Unit B-HC level 3 approved for cover, remaining level 3 to be inspected at a later date.
3rd floor tinting. Gerarrdo is the contact. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/28/2018 | 12/28/2018 | 12/28/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkler piping/tenting on north apartment units complete, approved for cover except unit B-HC on level 3, mentioned unit cannot be covered due to tenting issues.
|
INSP-Sprinkler Rough-in | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | FAIL |
Jim Page
|
|
|
Unit B-HC level 3 has exposed piping in the attis space where tenting was not installed correctly.
2nd half inspection. Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/26/2018 | 12/26/2018 | 12/26/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in north apartments levels 1 and 2 complete, approved for cover. Level 3 inspected but no tenting installed, no cover allowed for level 3.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Intake Approval | | | 10/31/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/31/2018 | | 10/31/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/31/2018 | | 10/31/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/31/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/31/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/31/2018 | | DONE |
|
|
|
|
Application received | | | 10/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 27 2018 2:46PM
|