INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. 2nd and 3rd floor flow switches have been repaired.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 7/29/2019 | 7/31/2019 | 7/31/2019 | A | FAIL |
Jim Page
|
|
|
Flow switches for levels 2 and 3 did not operate correctly during flow test.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 7/24/2019 | 7/30/2019 | 7/29/2019 | A | CANC |
Jim Page
|
|
|
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 3/6/2019 | 3/7/2019 | 3/7/2019 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, level 3 approved for cover.
Gabe Garduno is the contact for this RTC inspection for building E. He is requesting the inspection for the 3rd floor. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/5/2019 | 3/6/2019 | 3/6/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on level 3 witnessed, no pressure loss observed.
This is for a hydro only inspection. Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/5/2019 | 3/5/2019 | 3/5/2019 | A | FAIL |
Jim Page
|
|
|
Level 3 is not approved for cover, tenting has been removed in numerous areas, needs to be corrected before cover is approved.
|
INSP-Sprinkler Rough-in | 3/5/2019 | 3/5/2019 | 3/5/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on levels 1 and 2 complete, levels 1 and 2 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PART |
Jim Page
|
|
|
Hydrostatic test for level 1 and 2 witnessed, no pressure loss observed.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/15/2019 | 2/19/2019 | 2/19/2019 | A | FAIL |
Jim Page
|
|
|
Install does not match city approved drawings. Adjust hangers in areas that are overspaced.
Gerardo Arce is the contact. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Intake Approval | | | 10/31/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/31/2018 | | 10/31/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/31/2018 | | 10/31/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/31/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/31/2018 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 10/31/2018 | | DONE |
|
|
|
|
Application received | | | 10/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 27 2018 2:54PM
|