INSP-Final Inspection | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Todd Ketterling is the contact. This inspection should have already taken place, this is just the paper trail. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 10/15/2019 | 10/16/2019 | 10/16/2019 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled due to time constraints due to work load.Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2019 | 8/6/2019 | 8/6/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
|
INSP-Supply line flush | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Todd Ketterling is the contact. Stacey with Suez is aware of this inspection, he and Todd are working out a specific time to meet there. Please contact them for that time. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2019 | 7/19/2019 | 7/19/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed.
Troy Lowe is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining underground supply complete, approved for cover.
Bryan Collins is the contact. He has already been in contact with Jim Page who has agreed to have this done today, he just needed the paper trail. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids complete, hardlids approved for cover.
Jon Beazer is the contact. This rough-in is for the hard lids. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan assigned to (Stumbaugh) | 6/5/2019 | | 6/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
as built
|
Sprinkler Plan Check | 6/7/2019 | | 6/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
As Builts
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
As Built Drawings - No Fee
|
Permit Ready to Issue | | | 6/7/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 6/7/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/5/2019 | | DONE |
|
|
|
Per Kyle Kallmeyer - as built workflor
|
INSP-Sprinkler Rough-in | 5/24/2019 | 5/28/2019 | 5/28/2019 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, a cover inspection will be required for pendant heads/arm overs before cover can be approved.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/8/2019 | 1/8/2019 | 1/8/2019 | P | PART |
Jim Page
|
|
|
Rough to cover ins[pection for IBR complete, IBR approved for cover, remaining underground supply to be installed at a later date.
Bryan Collins is the contact for this underground RTC inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan resubmittals received | | | 11/9/2018 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/9/2018 | | 11/9/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/9/2018 | | 11/9/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/9/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/9/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/2/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/2/2018 | | 11/2/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/2/2018 | | 11/2/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/2/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/2/2018 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 10/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2018 1:47PM
|