DOC - Permit Finaled | | | 11/20/2019 | | DONE |
|
|
|
All requested documentation received and approved.
|
Miscellaneous action | | | 4/15/2019 | | DONE |
|
|
|
Received emails that John had with Honeywell tech support that indicated the system operates properly when notification disables are activated. Currently, the way it operates meets the UL certification of the product. Ok to final
|
INSP-Final Inspection | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | FAIL |
Troy Cobbley
|
|
|
Permit will be ok to final when documents are provided to plan review that address the supervisory/rrouble on panel as per revios corretion
John Howard, Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
CHANGE STATUS TO (ISS) | | | 3/20/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/18/2019 | | DONE |
|
|
|
|
1st review completed | | | 3/18/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 3/18/2019 | | 3/18/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/18/2019 | | DONE |
|
|
|
Plan mod passed. No additional review comments.
|
Permit Ready to Issue | | | 3/18/2019 | | DONE |
|
|
|
plan mod
|
INSP-Final Inspection | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for a list of required corrections.
Earl Lasater, Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
FIR-Aging Inspection | 2/28/2019 | 2/28/2019 | 2/28/2019 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type called in.
|
INSP-Alarm Testing | 2/28/2019 | 2/28/2019 | 2/28/2019 | P | DONE |
Troy Cobbley
|
|
|
Earl and I did a walk through of the Basement, first floor and second floor corridor system and verified horn/strobe spacing/height.
|
CHANGE STATUS TO (ISS) | | | 2/22/2019 | | DONE |
|
|
|
|
Staff review | 2/21/2019 | 2/21/2019 | 2/21/2019 | | DONE |
Lee G Meredith
|
|
|
|
Plan assigned to (Lee) | 2/21/2019 | | 2/21/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/21/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 2/21/2019 | | 2/21/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/21/2019 | | DONE |
|
|
|
Plan mod passed. No additional comments.
|
Permit Ready to Issue | | | 2/21/2019 | | DONE |
|
|
|
PLAN MOD
|
Miscellaneous action | | | 2/21/2019 | | DONE |
|
|
|
John requested the work flow be opened to upload a plan modificaiton.
|
Plan Modification Accepted | | | 2/21/2019 | | DONE |
|
|
|
as per Lee M-started 2nd plan mod and assigned to Lee and staff review
|
INSP-Final Inspection | 1/15/2019 | 1/16/2019 | 1/16/2019 | P | FAIL |
Troy Cobbley
|
|
|
No testing of devices performed today. Inspection was only for the Basement area. Plan modifications are needed showing the correct form of communication, fire sprinkler riser device count (delete dry system), strobes are too low, wall and ceiling mount devices do not corrispond with the plans, Storage Room needs notification device modifications, batteries in the FACP do not match plans. We discussed the function of the Basement duct smoke detectors in the Mechanical Room.
Earl Lasater, Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
Plan Modification Accepted | | | 1/11/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 1/11/2019 | | 1/11/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/11/2019 | | DONE |
|
|
|
Plan Mod passed. No additional review comments.
|
Permit Ready to Issue | | | 1/11/2019 | | DONE |
|
|
|
plan mod approved
|
Miscellaneous action | | | 1/10/2019 | | DONE |
|
|
|
John requested work flow be reopened for a plan mod.
|
Issue and Print Permit | | | 10/31/2018 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 10/30/2018 | | 10/30/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 10/30/2018 | | PASS |
|
|
|
Passed as noted on drawings.
|
Alarm Plan Check | 10/30/2018 | | 10/30/2018 | | DONE |
Lee G Meredith
|
|
|
|
Permit Ready to Issue | | | 10/30/2018 | | DONE |
|
|
|
|
Application received | | | 10/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2018 3:58PM
|