INSP-Final Inspection | 4/26/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Jim Page
|
|
|
AS-builts are approved, fire alarm matchs install, final fire alarm inspection complete.
Call prior to going Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Plan assigned to (Lee) | 4/18/2019 | | 4/23/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 4/23/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 4/23/2019 | | 4/23/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 4/23/2019 | | DONE |
|
|
|
As builts approved.
|
Permit Ready to Issue | | | 4/23/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/23/2019 | | DONE |
|
|
|
no fees. as build per lee
|
INSP-Final Inspection | 4/12/2019 | 4/15/2019 | 4/15/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need as-builts and calculations as per the review comments.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final yet due to the fire sprinkler contractor starting 2 hour hydro testing for the overhead and underground.
Call prior to going Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
Application received | | | 11/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 1 2018 9:21AM
|
Plan assigned to (Lee) | 11/1/2018 | | 11/1/2018 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 11/1/2018 | | DONE |
|
|
|
Drawing shows 3 choices for monitoring communications. I emailed Sheri to request a determination of which method will be used. Charlie responded to indicate they will use sole path cellular only.
|
1st review completed | | | 11/1/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 11/1/2018 | | 11/1/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/1/2018 | | DONE |
|
|
|
Plans passed with review comments and requirements noted on the drawings.
|
Permit Ready to Issue | | | 11/1/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/1/2018 | | DONE |
|
|
|
|