Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR18-00869
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 2404 W BANK DR Unit: 101
Project NameFifty Flowers - TI
Customer Number 
ePlanReviewYes
Description
[Fifty Flowers TI]
The fire sprinkler scope of work consists of removing part of an old CPVC system and replacing with a new larger steel pipe system. The new area has all upright sprinklers. The system is a gridded with 2”x1½” mains and 1¼” branch lines.

[BLD18-02699]
Temporary Occupancy through March 31st, 2019 ** Permit to remodel 4,477 sq ft for a new office tenant on the third floor of an existing office building and for work in the common areas, including the non-rated corridor and restrooms. The remaining 1,253 sq ft tenant suite is permitted for a temporary certificate of occupancy under BLD18-03786. Work to include: new offices with new interior non-bearing partition walls and doors, relocated HVAC, new roof top units, new data and lighting, new light switches with occupancy sensors, accessible upgrades to the restrooms, plumbing for restrooms and new kitchenette, and interior finishes to be in compliance with 2015 IBC Ch. 8. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the building’s Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 and NFPA 72 as regulated by the Boise Fire Department. Tenant to submit a building permit for permanent occupancy of the entire 3rd floor prior to March 31, 2019. **JAR**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/4/20191/7/20191/7/2019APASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.

Contact Hunter Anderson ###-#### 30 min prior to Fire Final Insp please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection1/3/20191/4/20191/4/2019AFAIL
DetailsJim Page
Provide fire sprinkler under duct where head is overspaced. Provide fire sprinkler next to duct work where head is blocked as discussed. All foil needs to be removed from heads before life fire safety inspection.

Contact Hunter Anderson ###-#### 30 Min prior to Fire Final Start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in12/28/201812/31/201812/31/2018AFAIL
DetailsTroy Cobbley
Todays inspection was just for the third floor west stairwell. Sheetrock texture/paint and installeation of sprinkler canopies is not complet. Ceiling missing at the second floor landing as well.

Hunter Phone #: ###-####
INSP-Sprinkler Rough-in12/21/201812/26/201812/26/2018APASS
DetailsJim Page
Rough to cover inspection for overehad fire sprinkler piping in area of work complete, approved for cover.

Contact Hunter Anderson ###-#### 30 min prior to RTC Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in12/20/201812/21/201812/21/2018PCANC
DetailsJim Page
Contact Hunter Anderson - ###-#### 30 Min prior to RTC Insp start please

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
Issue and Print Permit  12/3/2018 DONE
Sprinkler Plan Check11/30/2018 11/30/2018 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  11/30/2018 DONE
DetailsTim Frost
Permit Ready to Issue  11/30/2018 DONE
Intake Approval  11/21/2018 PASS
DetailsTim Frost
Plan assigned to (Tim)11/21/2018 11/21/2018 DONE
DetailsTim Frost
Sprinkler Plan Check11/21/2018 11/21/2018 FAIL
DetailsTim Frost
1st review completed  11/21/2018 FAIL
DetailsTim Frost
Miscellaneous action  11/21/2018 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  11/9/2018 DONE
Application submitted via PDS Online on Nov 9 2018 8:47AM