INSP-Final Inspection | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Please call Randy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
CHANGE STATUS TO (ISS) | | | 1/11/2019 | | DONE |
|
|
|
Accidentally changed to void. Restored to issued.
|
INSP-Sprinkler Rough-in | 1/8/2019 | 1/9/2019 | 1/9/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work on levels 1 and 4 complete, approved for cover.
Please call Randy Cartwright for this rough in inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Issue and Print Permit | | | 11/21/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/20/2018 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/20/2018 | | 11/20/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/20/2018 | | 11/20/2018 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/15/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/15/2018 | | 11/15/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/15/2018 | | 11/15/2018 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/15/2018 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 11/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 13 2018 11:47AM
|