INSP-Final Inspection | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Call James before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, overhead fire sprinkler piping approved for cover.
Tenting Inspection Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan assigned to (Stumbaugh) | 2/4/2019 | | 2/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/6/2019 | | 2/6/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 2/6/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 2/6/2019 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, overehad fire sprinkler piping installed between conditioned spaces approved for cover, piping in attic spaces requiring tenting not approved for cover until a tenting inspection is performed and approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2019 | 2/4/2019 | 2/4/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan Modification Accepted | | | 2/4/2019 | | DONE |
|
|
|
Adding a double check backflow device. Eplan workfow started.
|
Issue and Print Permit | | | 12/27/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/12/2018 | | 12/17/2018 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/17/2018 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 12/12/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/12/2018 | | 12/12/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 12/4/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 12/4/2018 | | 12/4/2018 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/4/2018 | | 12/4/2018 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/4/2018 | | DONE |
Tim Frost
|
|
|
Emailed failed review to applicant
|
1st review completed | | | 12/4/2018 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 11/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 29 2018 8:49AM
|