INSP-Final Inspection | 5/3/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact name is Raul Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | CANC |
Mark Scharfen
|
|
|
Alarmco not ready. Contact Raul Phone #: ###-#### >> Inspection requested via web by Chris Green
|
INSP-Final Inspection | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Permit will be ok to final when a FIR permit is issued/tested for the control valve tamper switch below the mezzanine.
Raul is the contact. Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in/Hydro | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered. Overhead hydro witnessed with no loss at the guage.
Contact Name is Raul. Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | PART |
Troy Cobbley
|
|
|
The general rough-in is ok except the Coin upright heads over the restrooms are installed too low as per the data sheet. Will need to restart the hydro due to the need to modify the pipe and heads.
POC is Raul Munoz Phone #: ###-#### Inspection requested via web by Chris Green
|
Plan assigned to (Stumbaugh) | 4/17/2019 | | 4/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/18/2019 | | 4/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 4/18/2019 | | DONE |
|
|
|
plan mod
|
CHANGE STATUS TO (ISS) | | | 4/18/2019 | | DONE |
|
|
|
plan mod-per MAS no plan mod fee
|
Plan Modification Accepted | | | 4/17/2019 | | DONE |
|
|
|
per Mark Stumbaugh
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2019 | 4/16/2019 | 4/16/2019 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test failed due to visible loss on guage. need plan mods due to added riser nipples, heads and sprig ups that have been added in the remote area under the mezzanine. No small documents or review notes on site. Inspection stopped.
Contact Name is Raul Munoz Phone #: ###-#### Inspection requested via web by Chris Green
|
Sprinkler Plan Check | 12/7/2018 | | 12/10/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/10/2018 | | 12/10/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 12/10/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/10/2018 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/10/2018 | | DONE |
|
|
|
|
Miscellaneous action | | | 12/7/2018 | | DONE |
Mark Stumbaugh
|
|
|
Emailed Chris Green requesting more info
|
Intake Approval | | | 12/7/2018 | | PASS |
Mark Stumbaugh
|
|
|
|
Application received | | | 12/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 5 2018 1:25PM
|