Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberFIR18-00918
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 11343 W PRESIDENT DR
Project NameInnovative Air
Customer Number 
ePlanReviewYes
Description
Owner is adding a mezzanine in the northeast corner of the building. Viking will tie into the existing 6" main with a 4" main to supply under the mezzanine. The building has an existing looped wet system. The area under the mezzanine is light hazard area, restrooms conference rooms and break area.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/3/20195/6/20195/6/2019PPASS
DetailsTroy Cobbley
Permit finaled

Contact name is Raul Phone #: ###-#### Inspection requested via web by Chris Green
INSP-Final Inspection5/2/20195/2/20195/2/2019PCANC
DetailsMark Scharfen
Alarmco not ready. Contact Raul Phone #: ###-#### >> Inspection requested via web by Chris Green
INSP-Final Inspection4/26/20194/29/20194/29/2019AFAIL
DetailsTroy Cobbley
Permit will be ok to final when a FIR permit is issued/tested for the control valve tamper switch below the mezzanine.

Raul is the contact. Phone #: ###-#### Inspection requested via web by Chris Green
INSP-Sprinkler Rough-in/Hydro4/23/20194/24/20194/24/2019APASS
DetailsTroy Cobbley
Rough-in passed. Piping can be covered. Overhead hydro witnessed with no loss at the guage.

Contact Name is Raul. Phone #: ###-#### Inspection requested via web by Chris Green
INSP-Sprinkler Rough-in/Hydro4/22/20194/23/20194/23/2019PPART
DetailsTroy Cobbley
The general rough-in is ok except the Coin upright heads over the restrooms are installed too low as per the data sheet. Will need to restart the hydro due to the need to modify the pipe and heads.

POC is Raul Munoz Phone #: ###-#### Inspection requested via web by Chris Green
Plan assigned to (Stumbaugh)4/17/2019 4/18/2019 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check4/18/2019 4/18/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  4/18/2019 DONE
DetailsMark Stumbaugh
No Fee
Permit Ready to Issue  4/18/2019 DONE
plan mod
CHANGE STATUS TO (ISS)  4/18/2019 DONE
plan mod-per MAS no plan mod fee
Plan Modification Accepted  4/17/2019 DONE
per Mark Stumbaugh
INSP-Sprinkler Rough-in/Hydro4/15/20194/16/20194/16/2019AFAIL
DetailsTroy Cobbley
Overhead hydro test failed due to visible loss on guage. need plan mods due to added riser nipples, heads and sprig ups that have been added in the remote area under the mezzanine. No small documents or review notes on site. Inspection stopped.

Contact Name is Raul Munoz Phone #: ###-#### Inspection requested via web by Chris Green
Sprinkler Plan Check12/7/2018 12/10/2018 DONE
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)12/10/2018 12/10/2018 DONE
DetailsMark Stumbaugh
1st review completed  12/10/2018 DONE
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  12/10/2018 DONE
DetailsMark Stumbaugh
Permit Ready to Issue  12/10/2018 DONE
Issue and Print Permit  12/10/2018 DONE
Miscellaneous action  12/7/2018 DONE
DetailsMark Stumbaugh
Emailed Chris Green requesting more info
Intake Approval  12/7/2018 PASS
DetailsMark Stumbaugh
Application received  12/5/2018 DONE
Application submitted via PDS Online on Dec 5 2018 1:25PM