INSP-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
This is scheduled for 7:00am Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 1/25/2019 | 1/28/2019 | 1/28/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Issue and Print Permit | | | 12/10/2018 | | DONE |
|
|
|
|
Application received | | | 12/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2018 1:35PM
|
Intake Approval | | | 12/6/2018 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/6/2018 | | 12/6/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 12/6/2018 | | 12/6/2018 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/6/2018 | | DONE |
|
|
|
|